(a)In determining whether an amendment to a license, construction permit, or early site permit will be issued to the applicant, the Commission will be guided by the considerations which govern the issuance of initial licenses, construction permits, or early site permits to the extent applicable and appropriate. If the application involves the material alteration of a licensed facility, a construction permit will be issued before the issuance of the amendment to the license, provided however, that if the application involves a material alteration to a nuclear power reactor manufactured under part 52 of this chapter before its installation at a site, or a combined license before the date that the Commission makes the finding under § 52.103(g) of this chapter, no application for a construction permit is required. If the amendment involves a significant hazards consideration, the Commission will give notice of its proposed action:
(1)Under § 2.105 of this chapter before acting thereon; and
(2)As soon as practicable after the application has been docketed.
(b)The Commission will be particularly sensitive to a license amendment request that involves irreversible consequences (such as one that permits a significant increase in the amount of effluents or radiation emitted by a nuclear power plant).
(c)The Commission may make a final determination, under the procedures in § 50.91, that a proposed amendment to an operating license or a combined license for a facility or reactor licensed under §§ 50.21(b) or 50.22, or for a testing facility involves no significant hazards consideration, if operation of the facility in accordance with the proposed amendment would not:
(1)Involve a significant increase in the probability or consequences of an accident previously evaluated; or
(2)Create the possibility of a new or different kind of accident from any accident previously evaluated; or
(3)Involve a significant reduction in a margin of safety. [51 FR 7767, Mar. 6, 1986, as amended at 72 FR 49504, Aug. 28, 2007]
Connections6,823 cite this
Cited by 6,823 sections · top 60
register
- NoticesNUCLEAR REGULATORY COMMISSION
- Rules and RegulationsBiweekly notice
- NoticesExemption; issuance
- Rules and RegulationsMonthly notice
- NoticesLicense amendment request; opportunity to comment, request a hearing, and petition for leave to intervene; order
- NoticesLicense amendment request; notice of opportunity to comment, request a hearing, and petition for leave to intervene; order imposing procedures
- Rules and RegulationsNUCLEAR REGULATORY COMMISSION
- NoticesExemption; issuance
- NoticesNotice
- NoticesNUCLEAR REGULATORY COMMISSION
- NoticesNUCLEAR REGULATORY COMMISSION
- NoticesLicense amendment application; opportunity to request a hearing and to petition for leave to intervene
- NoticesLicense amendment request; notice of opportunity to comment, request a hearing, and petition for leave to intervene; order imposing procedures
- NoticesNotice
- Rules and RegulationsNUCLEAR REGULATORY COMMISSION
- NoticesBiweekly notice
- NoticesNUCLEAR REGULATORY COMMISSION
- NoticesNUCLEAR REGULATORY COMMISSION
- NoticesLicense amendment application; opportunity to comment, request a hearing, and petition for leave to intervene; order
- NoticesBiweekly notice
- NoticesNUCLEAR REGULATORY COMMISSION
- NoticesMonthly notice
- NoticesBiweekly notice
- Rules and RegulationsNUCLEAR REGULATORY COMMISSION
- NoticesMonthly notice
- Rules and RegulationsNUCLEAR REGULATORY COMMISSION
- NoticesLicense amendment request; opportunity to comment, request a hearing, and petition for leave to intervene; order
- NoticesExemption
- NoticesLicense amendment request; opportunity to comment, request a hearing, and petition for leave to intervene; order
- NoticesLicense amendment request; opportunity to comment, request a hearing, and petition for leave to intervene; order imposing procedures
- NoticesMonthly notice
- NoticesNUCLEAR REGULATORY COMMISSION
- Rules and RegulationsNUCLEAR REGULATORY COMMISSION
- NoticesBiweekly notice
- Rules and RegulationsBiweekly notice
- NoticesNotice; issuance
- Notices60-Day notice of information collection under review: extension of previously approved collection; Department of Justice procurement blanket clearance
- Rules and RegulationsNUCLEAR REGULATORY COMMISSION
- NoticesBiweekly notice
- NoticesOrder and notice of license amendment request, opportunity to comment, opportunity to request a hearing
- NoticesLicense amendment request; opportunity to comment, request a hearing, and petition for leave to intervene; order
- Rules and RegulationsNUCLEAR REGULATORY COMMISSION
- NoticesRequest for comment
- Proposed RulesNUCLEAR REGULATORY COMMISSION
- NoticesMonthly notice
- NoticesNUCLEAR REGULATORY COMMISSION
- NoticesNUCLEAR REGULATORY COMMISSION
- NoticesNUCLEAR REGULATORY COMMISSION
- Proposed RulesNUCLEAR REGULATORY COMMISSION
- NoticesNUCLEAR REGULATORY COMMISSION
- NoticesNotice of Availability
- NoticesNotice of availability
- NoticesNUCLEAR REGULATORY COMMISSION
- NoticesNotice of cancellation of April 24, 2007 public hearing concerning a list of goods for which tariff concessions may be withdrawn and duties may be increased in the event the United States cannot reach agreement with the European Communities (EC) for adequate compensation owed under World Trade Organization (WTO) rules as a result of EU enlargement
- NoticesNotice of reopening of public comment period
- NoticesLicense amendment application; opportunity to comment, request a hearing, and petition for leave to intervene
- NoticesOpportunity to comment, request a hearing, and petition for leave to intervene
- NoticesBiweekly notice
- NoticesLicense amendment request; opportunity to comment and request a hearing, order
- NoticesNUCLEAR REGULATORY COMMISSION
Citation graph
cites case law
§ 50.92
Issuance of amendment.
Fed. Reg.×6,821
C.F.R.×2
Cites 0Cited by 6,823 across 2 sources